A Material Safety Data Sheet (MSDS) must be attached to offer submissions in accordance with FAR Clause 52.223-3.
| Update / Notice ID |
Description |
Posted Date |
Response Date |
| 0003
|
Amendment 0003: The purpose of this amendment is to extend the bid opening from 22 August 2024 to 06 September 2024. Amendment 0002: The purpose of this amendment is to answer the RFIs and update the drawings and specifications. |
2024/08/06 03:46 UTC |
2024-08-22 14:00 I1 Time Zone |
| 0002
|
Amendment 0002: The purpose of this amendment is to answer the RFIs and update the drawings and specifications. Amendment 0001: The RFI due date is extended to June 17th and the RFI Bidder Inquiry Key has been changed to 4K7KWN-G6GZ8W. |
2024/07/25 06:04 UTC |
2024-08-22 14:00 I1 Time Zone |
| 0001
|
Amendment 0001: The RFI due date is extended to June 17th and the RFI Bidder Inquiry Key has been changed to 4K7KWN-G6GZ8W.FY23 OMA Convert Vehicle Storage Warehouse B122-S1, Sagami General Depot project will provide Fire Protection Upgrades at exist |
2024/06/14 01:53 UTC |
2024-08-22 14:00 I1 Time Zone |
| W912HV24B0012
|
FY23 OMA Convert Vehicle Storage Warehouse B122-S1, Sagami General Depot project will provide Fire Protection Upgrades at existing Warehouse B122-S1, Sagami General Depot, Sagamihara, Kanagawa, Japan. The project facilities are currently occupied by |
2024/05/23 22:35 UTC |
2024-08-22 14:00 I1 Time Zone |